Remediation of the existing ground followed by the construction of 3 number 9 storey reinforced concrete frames and 1 number 6 storey reinforced concrete frame parallel to the London Underground railway tracks adjacent to Wembley Park Station.
Groundworks commenced in November 2013, with the RC frames due for completion in April 2014, based on an overall agreed programme duration of 35 weeks. We handed over the works 5 weeks early.
Following careful planning and close liaison between TFL, London Underground, Mulalley and ourselves we were able to work closely with all parties to agree a strategy that we could implement in order to construct the works safely and in a logical sequence. This was key to ensuring that all stakeholders were confident signing off method statements and also that all parties were fully conversant with the lifting plans, exclusion zones, tower crane restrictors and the logistics that were signed off to allow us to complete the works. This included daily reviews on site to ensure that no loose materials or debris could breach the neighbouring railway lines.
The site was initially remediated and then the enabling works were carried out including retaining walls and temporary access routes which were all completed prior to our main works commencing. The foundations were piled by others and then our groundworks commenced on the blocks in an agreed sequential manner.
The superstructure comprised 3 number 9 storey reinforced concrete blocks and 1 number 6 storey reinforced concrete block, using 800 Tonne of cut & bent reinforcement and 6,000 M3 of concrete.
External works were completed following the fitting of the brickwork façade and internal fit outs. This included the permanent road into site constructed using permeable pavement construction, stone filled gabions to retain the banks to the road side elevation, block paving and topsoil to communal areas and patios.
Modebest team take part in demanding cycle run from Clapham Common to Brighton in aid of Centrepoint Read more...
Modebest Builders are proud to be supporting the BBC DIY SOS programme as they build a brand-new home for the Dale Youth Boxing Club. Read more...
Modebest is proud to announce that we have constructed bespoke brand-new premises which we have called ‘MOY HOUSE’. Read more...
Modebest is moving to brand new premises with effect from 14th MAY 2018 Read more...
“We retain all of our own modern reinforced concrete frame equipment and falsework systems, our own tower cranes, concrete pumps and tipper lorries which enable us to be self-sufficient on our projects”
Moy House
69 Belvue Road
Northolt
Middlesex
UB5 5XS