Golf Links Estate, Southall

Client: Durkan Ltd
Value: £2.30M
Duration:Feb, 2014 – Oct , 2014 Subs & RC Frames 36 Weeks
Project Type: Groundwork and RC Frames

Project Description

The project entailed the construction of 5 number blocks of terraced housing and 2 number blocks of 6 storey low rise reinforced concrete frames forming 36 number houses and 26 number flats.

Scope of Works

We were engaged by Durkan as a domestic sub-contractor on an amended form of Sub-Contract, NEC 3 Engineering and Construction. We supplied a tower crane and attendant crane personnel to Durkan for this project.



The scope of works comprised reduced level dig, installation of a piling mat and piling attendance to the RC frame blocks, site waste management and removal of spoil from site, excavation and pouring mass concrete foundations up to 3.0m deep for the terraced housing blocks, substructure brickwork up to air brick level and precast concrete block and beam flooring to five terraced housing blocks, RC foundations and RC core, underslab drainage, site-wide drainage and services, deep drainage and 278 works connecting into existing estate drainage, two number low rise RC Frames, 6 storeys high, one RC core, 6 storeys high, interlinking steel bridge between the RC Blocks with metal decking and structural concrete topping, external works to front and rear gardens and the formation of a new road within the estate.



The scope of work entails:

  • Installation of a piling mat and piling attendance
  • Reduce level dig and foundation excavation
  • Site waste management and spoil disposal
  • Site logistics management
  • Supplying a tower crane
  • Providing tower crane attendant personnel
  • Underslab drainage
  • Site-wide drainage and services
  • Deep drainage and Section 278 works connecting to existing estate drainage
  • Excavation and pouring mass concrete foundations up to 3.00m deep to the housing blocks
  • Substructure brickwork up to air brick level in the terraced housing blocks
  • Precast concrete block and beam flooring to the terraced housing blocks
  • RC foundations and RC core foundations
  • 2 number low rise RC Frames, 6 storeys high
  • 1 number RC core, 6 storeys high
  • Metal decking and structural concrete topping to link bridge
  • External works to front and rear gardens
  • New estate road




 

Back...

 

orange stripes

0

Current Workforce

0

Projects Completed

0

Offices

Latest News

16th September 2018

Charity Bicycle Run from London to Brighton

Modebest team take part in demanding cycle run from Clapham Common to Brighton in aid of Centrepoint Read more...

5th September 2018

DIY SOS GRENFELL

Modebest Builders are proud to be supporting the BBC DIY SOS programme as they build a brand-new home for the Dale Youth Boxing Club. Read more...

14th May 2018

Modebest has Moved to Brand New Premises

Modebest is proud to announce that we have constructed bespoke brand-new premises which we have called ‘MOY HOUSE’. Read more...

27th April 2018

We Are Moving

Modebest is moving to brand new premises with effect from 14th MAY 2018 Read more...

“We are a ‘can-do’ company, who value long term relationships and repeat business. We are dependable and will deliver on our promises”

  • Achilles
  • Lighthouse Charity
  • Women into Construction
  • SMAS
T: + 44 (0) 20 8900 1981  |  F: + 44 (0) 20 8903 5238  |  E: info@modebest.co.uk
Specialists in: Groundworks | RC Frames | Civil Engineering
Specialists through: Expertise | Innovation | Competence | Safety